Number of employees

20

Man-hours worked

27 440

Installation volume, m²

3 520

man-hours worked

27 440

The new gas pipeline will be serviced by eight compressor stations, including Sivakinskaya CS-7. The compressor shop of the station is the center that pumps gas through pipes: here the “blue fuel” is cleaned, compressed, cooled and sent further. The main element of the compressor station is a gas pumping unit. There are three of them at Sivakinskaya - 25 MW each.

POLATI assembles RUX scaffolding, scaffolding structures with pipe and clamp connections, as well as suspended scaffolding structures at any height and of various complexity. The structures are installed for installation of suspended structures, pipelines, cable products.

Works on this project are complicated by climatic conditions in different seasons of the year, a large volume of work on a small area and a tight schedule of works.