Number of employees

20

Man-hours worked

27 440

Installation volume, m²

3 520

man-hours worked

27 440

The project involves the construction of three process lines for the production of liquefied natural gas (LNG) with a total capacity of 19.8 million tons per year and stable gas condensate up to 1.6 million tons per year.

The project is being realized in an innovative construction concept using gravity type foundations (GGFs). The absence of LNG plant construction works at the location of the LNG plant allows to significantly minimize the environmental impact.

Due to the northern conditions and the application of the latest energy efficiency technologies, greenhouse gas emissions per ton of LNG produced will be more than 30% below the industry average.

POLATI provides services to perform scaffolding erection and dismantling, insulation work, maintenance of buildings and structures in the factory.