2 126The project implemented in the spring of 2020 was part of a large-scale program aimed at modernizing existing facilities with the participation of international contractors. At this site, POLATI carried out the erection and dismantling of scaffolding to enable the subsequent installation of steel structures and equipment for the coke-cutting system.
The project was distinguished by a number of engineering complexities: the zero mark was at a height of 70 meters, and storage areas were limited. To avoid intersections with existing structures, the company's engineers conducted preliminary surveys and developed a detailed project. Material lifting was organized simultaneously with its installation.
Man-hours of work
Number of employees
491Number of engineers and technicians
59Volume of completed works, m³
4 000 000The project implemented in the spring of 2020 was part of a large-scale program aimed at modernizing existing facilities with the participation of international contractors. At this site, POLATI carried out the erection and dismantling of scaffolding to enable the subsequent installation of steel structures and equipment for the coke-cutting system.
The project was distinguished by a number of engineering complexities: the zero mark was at a height of 70 meters, and storage areas were limited. To avoid intersections with existing structures, the company's engineers conducted preliminary surveys and developed a detailed project. Material lifting was organized simultaneously with its installation.